Of the 12 core activities in the construction of a house for Manuel that has been carried out well, namely filling and foundation, on average this development has achieved 10% progress in the field. However, all kinds of materials needed are already available in different locations and are being worked on such as solid column iron and solid beam iron. The percentage of this calculation refers to the construction site that has been done, While the calculation of the percentage of jobs in different locations is not calculated.
The remaining 70% of the subgrade will be backfilled when the building sloof has been completed, and for the foundation using anchors the remainder will be calculated when the work is complete or when the 20 cm casting is completed. Below is a table of work to be done with the average percentage calculated according to construction engineering analysis
Number | Type of work | Progress |
---|---|---|
1 | Heap | 70% |
2 | Foundation | 50% |
3 | Sloof | 0% |
4 | Columns | 0% |
5 | Beams | 0% |
6 | Floor | 0% |
7 | Wall | 0% |
8 | Doors and Windows | 0% |
9 | Roof | 0% |
10 | Plafond | 0% |
11 | Electrical | 0% |
12 | Painting | 0% |
Progress | Current Average | 10% |
For more clarity, let's look at the table that I share below.
Perspective | Shop Drawing | Present Condiition |
---|---|---|
Front and Right Side View | ||
Front and Left Side View | ||
Back and Right Side View | ||
Back and Left Side View |
Project Name | Housing Project |
---|---|
Beneficiary | Manuel and Family |
Address | Venezuela |
Important notes in this development are as follows:
- I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
- Financial Update will be done by @mariana4ve
- I will analyze the progress of this construction progress before I publish it and according to technical regulations.
- Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
- Update construction at least once a week
This is the first progress update for the construction of a house to Manuel in Venezuela from the World Smile Project.
Previous progress post link
Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil