Progress increase from before was 15% (From 20% to 35%)
Of the 12 main activities carried out on the construction of a house for Manuel in Venezuela, 5 of them are being carried out by workers namely embankment which has a hoarded land of 70%, foundation work of 80%, 100 columns or pillars, 70% beams and 100% roof. Two of the five works being carried out have been 100% completed, while the other three which include hoarder land, foundation and beam are still in the work stage considering that the Hoarded land and foundation will be completed when the sloof and floor work has been completed, while the beams will be completed when installed. wall work and installation of door and window frames is completed or is being worked on later.
The next target of work that will be carried out and will take several working days is the installation of pipes as a substitute for sloof, the rest of the Hoarded land and floor casting. Then the wall work will also be carried out along with the installation of door and window frames. This is the progress analysis of the construction of a house for Manuel that I can present, and for more details on each work carried out, you can see as shown in the table below.
Number | Type of work | Progress |
---|---|---|
1 | Hoarded land | 70% |
2 | Foundation | 80% |
3 | Sloof | 0% |
4 | Columns | 100% |
5 | Beams | 70% |
6 | Floor | 0% |
7 | Wall | 0% |
8 | Doors and Windows | 0% |
9 | Roof | 100% |
10 | Ceiling | 0% |
11 | Electrical | 0% |
12 | Painting | 0% |
Progress | Current Average | 35% |
For more clarity, let's look at the table that I share below.
Perspective | Present Condiition |
---|---|
Front | |
Front and Right View | |
Front and Left View | |
Back and Right View | |
Back and Left View | |
Back |
Project Name | Housing Project |
---|---|
Beneficiary | Manuel and Family |
Address | Venezuela |
Important notes in this development are as follows:
- I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
- Financial Update will be done by @mariana4ve
- I will analyze the progress of this construction progress before I publish it and according to technical regulations.
- Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
- Update construction at least once a week
This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.
Previous progress post link
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 23, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 17, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - AUGUST 28, 2021
Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil